Program Command Center Sidera I · Digital Engineering Platform

Status 20 Nov 2026 Sprint 30 · PI 5 Next review CDR 30 Nov
★Mission statusProgram pulse
10days to CDR

Critical Design Review · Mon 30 Nov 2026 · dry run Mon 23 Nov · *TBR

0.79SPI (EVM)
0.96CPI · EAC $4.47M
+6 dPRR forecast 19 Aug 27
2High risks · RK-04, RK-25
4Open defects
26/32Artifacts released
Open schedule ↗
DTDigital twin3-D · 17 parts
17Parts
14Components
14Interfaces
35%Twin build
Spin it ↗
PIntegrated Master ScheduleProject-style · 62 tasks
Open Gantt ↗
RRisk registerTableau-style
25Open risks
2High
$2.20MExpected exposure
Explore ↗
TTest managementTestRail

115 cases · 14 runs · TE-01 starts 28 Dec

Run tests ↗
JWBS agile board · Sprint 30Jira-style · 665 issues
37Points left of 75
52Avg velocity

Goal: close CDR design package; burn down DR-0001 to DR-0004

Open board ↗
fxSystem design tool9 linked budgets
Change inputs ↗
ACAD drawingsAutoCAD

6 drawings · SID-1000 → 5000 · DXF export

Open .dwg ↗
OTSCollaborationMail · chat · minutes
52Minutes filed
44Open actions
3Unread mail
Open workspace ↗
DSRS · DOORS97 reqs

13 primary · 51 secondary · 33 tertiary

42TBD / TBR
48By test
Trace ↗
MModel set (Cameo-style)4 viewers
64Use cases
50Activities
153Functions
50States
WPLM · configWindchill

26 released · 3 review · 3 in work

32Artifacts
4Open CRs
Browse ↗